August 2009
August 2009
Internal fit-out of plumbing, electrical and mechanical services in the Studio Underground continues while finishings on the Rehearsal Rooms is in progress.
The internal walls to the main drum of Heath Ledger Theatre are visible and construction of the stairwells and lighting slots is underway. Steelwork for the roof of Heath Ledger Theatre is under manufacture.
In August work will commence to load the flying system equipment into the winch-rooms of the fly tower. Following this the mechanical services will be loaded before the structure for the roof of the fly tower is installed.
Work on the loading dock driveway is near completion and construction on the William Street buildings and upper gallery continues.
The tender for the technical theatre equipment has been released and research into communication systems that will best serve The Centre is ongoing.