November 2009

Feature image
Showcasing the pre-eminent art collection in Western Australia

November 2009

November 2009

The powered flying system is being installed in the fly-tower and fit-out of the tower cladding will soon be underway.

In Heath Ledger Theatre the orchestra-pit lift is being installed. The final pre-cast panels outside the theatre are being completed and the concrete slab to the theatre roof will soon be cast.

The large acoustic doors to separate the scene dock from Heath Ledger Theatre will be in place in early November.

Glazing and temporary carpet to the William Street buildings is being fitted and once complete, the John Holland project team and contractors will move into the upper level of the William Street building to free up the Chester Building for renovations.

In December the main crane for the site will be removed and this will make way for the bronze box at the entry to be completed and for the glazing along Roe Street to commence.